Control
valve Ensure
that the control valve is kept in its packaging and free of dust
and debris until installation. The sensor head and faceplate of
the valve should be stored in the box, ready for fixing upon completion
of the work. Equator
PE-X pipe PE-X
pipe and fittings must be protected from UV degradation as prolonged
exposure to sunlight could affect the longevity of the material.
Products stored internally or within sealed product packs or installed
within the building will not be at risk. Short-term exposure to
UV on building sites will not affect the PE-X products.
Coils should
be stored either on edge or stacked flat one on top of the other,
and provided with suitable racking to ensure stability. When coils
are vertically stacked, the stack height must not exceed 2m. An
80m coil of 15mm Equator pipe weighs 5.92kg. Equator
fittings Fittings
should be kept within the polythene bags wherever possible. Bare
fittings should be stored in a clean environment. When handling
or storing bare fittings do not allow any objects to slide into
the socket to avoid damage to the joint internals. Floor
panels and edge insulation strip These
products should not be stored or laid in wet or damp conditions.
The floor panel has a thermal conductivity of 0.033 to 0.036W/(m.k)
at +10ºC, measured to DIN52612. The compressive strength of the
floor panel under 10% compression is 0.11 to 0.16N/mm2, measured
to DIN53421. Long term compressive stress <2% compression is 0.025
to 0.040N/mm2.